Operations Management > QUESTIONS & ANSWERS > University of Houston, Downtown - MGT 3332. Chapter16 Solutions. All Answers Provided. See Questions (All)

University of Houston, Downtown - MGT 3332. Chapter16 Solutions. All Answers Provided. See Questions in the Description.

Document Content and Description Below

Chapter16 Solutions 6. Given: The following table contains information on four jobs waiting for processing at a work center (the jobs are listed in the order of their arrival): a. Determine job... sequence for (1) FCFS, (2) SPT, (3) EDD, and (4) CR: At day 21 + 6 = 27 [Job D completed], only Job B remains. Job B is scheduled fourth and will be completed on day 27 + 10 = 37. b. For each of the methods above, determine the (1) average flow time, (2) average tardiness, and (3) average number of jobs at the work center. Job flow time = Time it takes from when job arrives (day 0 in this problem) until it is complete. Tardiness = Flow time – Due date (0 if negative). Average number of jobs = Total flow time / Makespan. Makespan = Total of job times. c. SPT is superior because it provides the lowest value for each of the three measures. 7. Given: The following table contains information on five jobs waiting for processing at a work center (the jobs are listed in the order of their arrival): Job flow time = Time it takes from when job arrives (hour 0 in this problem) until it is complete. Tardiness = Flow time – Due date (0 if negative). Average number of jobs = Total flow time / Makespan. Makespan = Total of job times. FCFS Sequence: a-b-c-d-e Average job flow time = Total job flow time / Number of jobs = 87 / 5 = 17.40 hours. Average job tardiness = Total job tardiness / Number of jobs = 26 / 5 = 5.20 hours. Average number of jobs = Total flow time / Makespan = 87 / 32 = 2.72 jobs. SPT Sequence: c-b-a-e-d Average job flow time = Total job flow time / Number of jobs = 74 / 5 = 14.80 hours. Average job tardiness = Total job tardiness / Number of jobs = 27 / 5 = 5.40 hours. Average number of jobs = Total flow time / Makespan = 74 / 32 = 2.31 jobs. EDD Sequence: a-b-c-e-d Average job flow time = Total job flow time / Number of jobs = 84 / 5 = 16.80 hours. Average job tardiness = Total job tardiness / Number of jobs = 23 / 5 = 4.60 hours. Average number of jobs = Total flow time / Makespan = 84 / 32 = 2.63 jobs. Critical Ratio: CR Calculations (round to 2 decimals): CR=(Time Remaining Until Due Date)/(Processing Time Remaining) Initial critical ratios at hour 0: Job a is scheduled first. Job b is scheduled second. At hour 7 + 4 = 11 [Job b completed], the critical ratios are: Jobs c & e are tied for lowest. We will break the tie arbitrarily and schedule Job c third. The alternate solution scheduling Job e third is shown below. Alternate Critical Ratio Solution: Critical Ratio: CR Calculations (round to 2 decimals): 9. Given: A wholesale grocery distribution system uses a two-step process to fill orders. Tomorrow’s work will consist of filling the seven orders shown below. Determine a job sequence that will minimize the time required to fill the orders: We will use Johnson’s rule to sequence the jobs. The Johnson’s rule steps from the text are shown below: 1. Select the job with the shortest time. If the shortest time is at the first work center, schedule that job first; if the time is at the second work center, schedule the job last. Break ties arbitrarily. 2. Eliminate the job and its time from further consideration. 3. Repeat steps 1 and 2, working toward the center of the sequence, until all jobs have been scheduled. (a) Order C has the shortest time (0.80). Because the time is at Step 2, schedule Order C last (7th). Eliminate Order C from further consideration. (b) Order B has the shortest time (0.90). Because the time is at Step 1, schedule Order B first (1st) . Eliminate Order B from further consideration. (c) Order A has the shortest time (1.20). Because the time is at Step 1, schedule Order A toward the beginning of the sequence (2nd). Eliminate Order A from further consideration. (d) Order G has the shortest time (1.30). Because the time is at Step 1, schedule Order G toward the beginning of the sequence (3rd). Eliminate Order G from further consideration. (e) Order D has the shortest time (1.50). Because the time is at Step 2, schedule Order D toward the end of the sequence (6th). Eliminate Order D from further consideration. (f) Order E has the shortest time (1.60). Because the time is at Step 1, schedule Order E toward the beginning of the sequence (4th). Eliminate Order E from further consideration. (g) Order F is the only order remaining. Schedule Order F 5th. Eliminate Order F from further consideration. The final schedule is shown below: 10. Given: The times required to complete each of 8 jobs in a two-machine flow shop are shown in the table below. Each job must follow the same sequence, beginning with Machine A and moving to Machine B. a. Determine a sequence that will minimize makespan time: We will use Johnson’s rule to sequence the jobs. The Johnson’s rule steps from the text are shown below: 1. Select the job with the shortest time. If the shortest time is at the first work center, schedule that job first; if the time is at the second work center, schedule the job last. Break ties arbitrarily. 2. Eliminate the job and its time from further consideration. 3. Repeat steps 1 and 2, working toward the center of the sequence, until all jobs have been scheduled. (a) Job e has the shortest time (2). Because the time is at Machine A, schedule Job e first (1st). Eliminate Job e from further consideration. (b) Job b has the shortest time (3). Because the time is at Machine A, schedule Job b toward the beginning of the sequence (2nd). Eliminate Job b from further consideration. (c) Job f has the shortest time (4). Because the time is at Machine B, schedule Job f last (8th). Eliminate Job f from further consideration. (d) Job a has the shortest time (5). Because the time is at Machine B, schedule Job a toward the end of the sequence (7th). Eliminate Job a from further consideration. (e) Job c has the shortest time (6). Because the time is at Machine B, schedule Job c toward the end of the sequence (6th). Eliminate Job c from further consideration. (f) Job d has the shortest time (7). Because the time is at Machine B, schedule Job d toward the end of the sequence (5th). Eliminate Job d from further consideration. (g) Job h has the shortest time (11). Because the time is at Machine B, schedule Job h toward the end of the sequence (4th). Eliminate Job h from further consideration. (h) Job g is the only job remaining. Schedule Job g 3rd. Eliminate Job g from further consideration. The final schedule is shown below: b. Construct a chart of the resulting sequence, and Machine B’s idle time: c. Determine how much Machine B’s idle time would be reduced by splitting the last two jobs After splitting, we obtain the following Gantt chart: After splitting, Machine B’s idle time is = 2 + 1 + 5.5 + 3.5 + 4 = 16 hours, and the new makespan = 90. Machine B’s idle time would be reduced by 2 hours (18 – 16). 11. Given: Given the operation times provided: a. Develop a job sequence that minimizes idle time at the two work centers. We will use Johnson’s rule to sequence the jobs. The Johnson’s rule steps from the text are shown below: 1. Select the job with the shortest time. If the shortest time is at the first work center, schedule that job first; if the time is at the second work center, schedule the job last. Break ties arbitrarily. 2. Eliminate the job and its time from further consideration. 3. Repeat steps 1 and 2, working toward the center of the sequence, until all jobs have been scheduled. (a) Job D has the shortest time (12). Because the time is at Center 2, schedule Job D last (6th). Eliminate Job D from further consideration. (b) Job B has the shortest time (16). Because the time is at Center 1, schedule Job B first (1st). Eliminate Job B from further consideration. c) Job A has the shortest time (20). Because the time is at Center 1, schedule Job A toward the beginning of the sequence (2nd). Eliminate Job A from further consideration. (d) Job F has the shortest time (24). Because the time is at Center 2, schedule Job F toward the end of the sequence (5th). Eliminate Job F from further consideration. (e) Job E has the shortest time (28). Because the time is at Center 2, schedule Job E toward the end of the sequence (4th). Eliminate Job E from further consideration. (f) Job C is the only job remaining. Schedule Job C 3rd. Eliminate Job C from further consideration. The final schedule is shown below: b. Construct a chart of the activities at the two centers, and determine each one’s idle time: Center 1: 0 minutes of idle time. Center 2: 16 + 6 + 34 = 56 minutes of idle time. [Show More]

Last updated: 1 year ago

Preview 1 out of 19 pages

Add to cart

Instant download

We Accept:

We Accept
document-preview

Buy this document to get the full access instantly

Instant Download Access after purchase

Add to cart

Instant download

We Accept:

We Accept

Reviews( 0 )

$13.00

Add to cart

We Accept:

We Accept

Instant download

Can't find what you want? Try our AI powered Search

OR

REQUEST DOCUMENT
145
0

Document information


Connected school, study & course


About the document


Uploaded On

Feb 17, 2021

Number of pages

19

Written in

Seller


seller-icon
Kirsch

Member since 4 years

905 Documents Sold


Additional information

This document has been written for:

Uploaded

Feb 17, 2021

Downloads

 0

Views

 145

Document Keyword Tags


$13.00
What is Browsegrades

In Browsegrades, a student can earn by offering help to other student. Students can help other students with materials by upploading their notes and earn money.

We are here to help

We're available through e-mail, Twitter, Facebook, and live chat.
 FAQ
 Questions? Leave a message!

Follow us on
 Twitter

Copyright © Browsegrades · High quality services·